Free Fare Quarterly Report: April to June 1990

Free Fare Demonstration

Project Review
(April - June 1990)

By Capital Metro

-MEMORANDUM-
TO: Chairperson and Members of the Board of Directors
FROM: Anthony M. Kouneski, General Manager
DATE: August 7, 1990
SUBJECT: Free Fare Demonstration Project Review
(April - June 1990)
 

Please find attached an evaluation of the third three months (April - June 1990) of the Free Fare Demonstration Project. The format of this report follows that established for two previous reports which you have received.

If you would like additional information, please let me know.

Thank you.

TMK:HG/pm

Attachment

 

FREE FARE DEMONSTRATION
PROJECT REVIEW
April - June 1990

 

TABLE OF CONTENTS

Ridership Trends  
     Average Weekday Ridership Page 1
Performance Indicators  
     Passengers per Revenue Hour Page 1
     Passengers per Revenue Mile Page 3
     Cost per Vehicle Mile Page 3
     Cost per Vehicle Hour Page 3
     Cost per Passenger Page 4
     Cost per Revenue Hour Page 4
     Cost per Revenue Mile Page 4
Information Calls/Passenger Complaints  
     Information Calls Page 6
     Complaints Received Page 6
     Ratio of Complaints/1,000 Passengers Page 6
     Percentage Breakdown of Complaints Page 8
Security Incidents/Passenger Accidents  
     Summary of Security Incidents Page 9
     Ratio of Passenger Accidents/1,000,000 Riders Page 10
     Ratio of Vehicular Accidents/100,000 Miles Page 12
     Ratio of Passenger Accidents/100,000 Miles Page 14
Public Opinion  
     Results of Free Fare Public Hearing Page 16

 

FREE FARE DEMONSTRATION PROJECT
SECOND QUARTER REVIEW
JANUARY - MARCH 1990

 

RIDERSHIP TRENDS

Average Weekday Ridership
(less STS and UT Shuttle)

Month Ridership Percent Change
April 1990 77,215 + 83.4%
April 1989 42,107  
     
May 1990 76,265 + 76.3%
May 1989 43,256  
     
June 1990 77,962 + 84.8%
June 1989 42,179  
     
April - June 1990 77,147 + 81.4%
April - June 1989 42,514  

 

PERFORMANCE INDICATORS

Passengers per Revenue Hour
(less STS and UT Shuttle)

Month Passengers Percent Change
April 1990 47.11 + 86.6%
April 1989 25.25  
     
May 1990 45.06 +74.9%
May 1989 25.77  
     
June 1990 43.99 +74.9%
June 1989 25.15  
     
April - June 1990 45.39 + 78.8%
April - June 1989 25.39  

Average Weekday Ridership

Average Weekly Ridership

 

Passengers per Revenue Mile
(less STS and UT Shuttle)

Month Passengers Percent Change
April 1990 3.11 + 80.8%
April 1989 1.72  
     
May 1990 3.03 + 73.17%
May 1989 1.75  
     
June 1990 3.00 + 75.4%
June 1989 1.71  
     
April - June 1990 3.05 + 76.3%
April - June 1989 1.73  

 

Cost Per Vehicle Mile
(less UT)

Month Cost Percent Change
April 1990 2.78 + 0.77%
April 1989 2.80  
     
May 1990 3.38 + 9.77%
May 1989 3.08  
     
June 1990 2.73 - 11.4%
June 1989 3.06  
     
April - June 1990 2.96 - 0.8%
April - June 1989 2.98  

 

Cost Per Vehicle Hour
(less UT)

Month Cost Percent Change
April 1990 42.56 + 4.7%
April 1989 40.66  
     
May 1990 51.07 + 14.%
May 1989 44.65  
     
June 1990 40.32 - 9.0%
June 1989 44.29  
     
April - June 1990 44.65 + 3.4%
April - June 1989 43.20  

 

Cost Per Passenger
(less UT)

Month Cost Percent Change
April 1990 1.36 - 43.6%
April 1989 2.41  
     
May 1990 1.70 - 34.6%
May 1989 2.60  
     
June 1990 1.33 - 49.0%
June 1989 2.61  
     
April - June 1990 1.46 - 42.4%
April - June 1989 2.59  

 

Cost Per Revenue Hour
(less UT)

Month Cost Percent Change
April 1990 51.47 + 5.6%
April 1989 48.73  
     
May 1990 61.53 + 15.2%
May 1989 53.39  
     
June 1990 47.97 - 9.3%
June 1989 52.88  
     
April - June 1990 53.66 + 3.9%
April - June 1989 51.67  

 

Cost Per Revenue Mile
(less UT)

Month Cost Percent Change
April 1990 3.20 - 0.6%
April 1989 3.22  
     
May 1990 3.87 + 9.3%
May 1989 3.54  
     
June 1990 3.10 - 11.9%
June 1989 3.52  
     
April - June 1990 3.39 - 1.2%
April - June 1989 3.43  

Cost Per Passenger

Cost Per Passenger

 

INFORMATION CALLS/PASSENGER COMPLAINTS

Information Calls (474-1200)

Month Calls Handled Percent Change
April 1990 63,601 + 48.0%
April 1989 43,033  
     
May 1990 69,795 + 46.0%
May 1989 47,912  
     
June 1990 81,047 + 53.0%
June 1989 52,592  
     
April - June 1990 214,443 + 49.0%
April - June 1989 143,897  

 

Complaints Received

Month No. of Complaints Percent Change
April 1990 761 + 19.0%
April 1989 641  
     
May 1990 678 + 41.0%
May 1989 481  
     
June 1990 808 + 78.0%
June 1989 454  
     
April - June 1990 2,247 + 43.0%
April - June 1989 1,576  

 

Ratio of Complaints per 1,000 Passengers

Month # Complaints Ridership Complaints/1,000 Riders
April - June 1990 2,247 5,875,195 .382 / 1000
April - June 1989 1,576 3,252,449 .485 / 1000

Information Calls (474-1200)

Information Calls

 

Percentage Breakdown of Complaints

10 Most Frequent Categories

April - June 1990

Complaints Breakdown, 1990

April - June 1990

Complaints Breakdown, 1989

 

SECURITY INCIDENTS

An increase in security incidents was reported during the third three months of the Free Fare Program. A major contributing factor to the increase in incidents was due to the beginning of summer vacation for all levels of school age children. However, due to continuing incidents, security staffing has been increased - particularly in areas where special attention is required. In response, the security program has been revised to meet these changing conditions. Coverage has been increased on weekend nights. A detail has been established at the North Lamar Transit Center to closely monitor suspected gang activities at this 1ocation. A summary of reported security incidents is provided below:

Type of Incident Oct - Dec
1989
Jan - March
1990
April - June
1990
Rocks or other objects thrown 26 19 24
Disputes between passengers with no injuries and disputes between passengers with injuries 32 22 38
Operator assaults with no injuries 6 3 2
Operator assaults with injuries 1 2 4
Operators verbally abused 15 26 31
Intoxicated passengers 21 29 69
Vandalism on buses 13 6 8
Weapons on buses 6 5 2
Other 0 0 15
TOTAL 120 119 193

 

CAPITAL METRO
PSGR. ACCIDENTS PER 1,000,000 PSGRS.
1986 THROUGH 1989

Passenger Accidents per 1 mil Passengers

 

PASSENGER ACCIDENTS
PER 1,000,000 PASSENGERS

Passenger Accidents per 1 mil Passengers

1990 Budget: 11.5

Definition: Passenger type accidents involving revenue vehicles (per 1,000,000 vehicles)

CURRENT MONTH

YEAR-TO-DATE

  1990
Actual #
1990
Actual %
1989
Actual %
  1990
Actual #
1990
Actual %
1989
Actual %
JAN 18 10.0 20.4   18 10.0 20.4
FEB 21 12.4 13.7   39 11.1 17.2
MAR 27 14.2 15.5   66 12.2 16.8
APR 21 11.7 15.0   87 12.1 16.3
MAY 18 9.5 18.5   105 11.5 17.1
JUN 10 5.4 26.5   115 10.5 18.4
JUL     19.0       18.5
AUG     21.8       19.0
SEP     19.1       18.9
OCT     11.1       17.7
NOV     12.4       17.1
DEC     10.7       16.3

 

CAPITAL METRO
VEHICULAR ACCIDENTS PER 100,000 MILES
1985 THROUGH 1989

Vehicular Accidents per 100k Passengers

 

TOTAL VEHICULAR ACCIDENTS
PER 100,000 MILES

Vehicular Accidents per 100k Passengers

 

1990 Budget: 3.2

Definition: Collision type accidents involving revenue vehicles

CURRENT MONTH

YEAR-TO-DATE

  1990
Actual #
1990
Actual %
1989
Actual %
  1990
Actual #
1990
Actual %
1989
Actual %
JAN 28 3.8 2.8   28 3.8 2.8
FEB 17 2.5 4.4   45 3.2 3.6
MAR 19 2.4 2.3   64 2.8 3.2
APR 25 3.2 3.7   89 3.0 3.5
MAY 18 2.3 4.1   107 2.8 4.1
JUN 22 2.8 3.1   129 2.8 3.5
JUL     3.2       3.3
AUG     3.4       3.4
SEP     4.0       3.4
OCT     3.7       3.5
NOV     2.4       3.4
DEC     3.5       3.4

 

CAPITAL METRO
PASSENGER ACCIDENTS PER 100,000 MILES
1986 THROUGH 1989

Passenger Accidents per 100k Passengers

 

PASSENGER ACCIDENTS
PER 100,000 MILES

Passenger Accidents per 100k Passengers

 

1990 Budget: 2.4

Definition: Passenger type accidents involving revenue vehicles (per 100,000 miles)

CURRENT MONTH

YEAR-TO-DATE

  1990
Actual #
1990
Actual %
1989
Actual %
  1990
Actual #
1990
Actual %
1989
Actual %
JAN 18 2.4 2.7   18 2.4 2.7
FEB 21 3.1 1.7   39 2.8 2.2
MAR 27 3.4 2.2   66 3.0 2.2
APR 21 2.7 2.2   87 2.9 2.2
MAY 18 2.3 2.7   105 2.8 2.3
JUN 10 1.3 3.6   115 2.5 2.5
JUL     2.5       2.5
AUG     3.2       2.6
SEP     3.0       3.0
OCT     2.6       2.6
NOV     2.7       2.6
DEC     2.1       2.6

 

FREE FARE PUBLIC HEARING

On Monday, April 30, a public hearing on the Free Fare Demonstration Program was held in the Capital Metro Board Room. The hearing was publicized through newspaper and radio advertisements, passenger notices, postings on buses, a public (newspaper) notice and distribution of a press release.

Forty-five people attended the meeting, with 31 of those people speaking before the Board. Seventeen speakers supported continuation of free fares, while 12 speakers advocated reinstituting fares before the end of 1990. (Two speakers spoke on other unrelated matters.)

Twenty of the 31 speakers stressed the importance of effective security measures. Seven speakers referred to truancy and other problems related to young riders. Other issues mentioned operators, buses running off schedule, the need to maintain service quality and the value of maximizing revenues through the collection of fares.

Seven speakers asked the Board to consider reduced fares and/or substantially reduced pass prices should fares be reintroduced. Two speakers asked that fares be waived for selected groups such as individuals with low incomes.

A petition, signed by 215 bus operators, was presented at the meeting. It called for reinstatement of fares as soon as possible. The petition cited "an increase in attacks and incidents on all Capital Metro buses, causing undue stress and delays to both passengers and bus operators".

Summary

Based on marketing surveys conducted at the beginning of this period, the public hearing, and input received through the Passenger Assistance Center, there appeared to be support for continuation of free fares through 1990. However, there was also considerable support for increased security measures.

In response, staff has undertaken the following actions: Uniformed security patrols now provide mobile, on-demand coverage of the service area 165 hours per week. In addition, these services have been augmented with undercover officers 60 hours per week. Another 30 hours per week is dedicated to the N. Lamar Transit Center. The undercover activity is aimed at deterring problems on the buses through uncertainty. All services are provided between the hours of 12:00 p.m. and 1:00 a.m., Monday through Saturday, and 12;00 p.m. and 9:00 a.m. on Sunday. Finally, specific problem areas are handled with additional coverage as determined by input from operators and concerned patrons.

AttachmentSize
farefreequarterly_aprjune1990.pdf802.66 KB

Recent News